Grid and interconnection
Queue timing, transmission, substations, deliverability, utility obligations, and the gap between announced power and executable service.
Frontier Grid tracks the rules, caps, queues, financial gates, and physical dependencies that determine whether a large load can actually get onto the system at the required scale and date.
A public view of governed access mechanisms across U.S. RTOs, ERCOT, Brazil, and Alberta. The values below come from human-reviewed durable records rather than staging proposals or inferred capacity.
Open Compute Intelligence| Case | Stage | Requested | Connectable | Cap | Next gate | Checked |
|---|---|---|---|---|---|---|
PJM EL26-67 | filed change: yes | — | — | — | Nov 16, 2026 | Aug 26, 2026 |
SPP EL26-68 | filed change: yes | — | — | — | Nov 20, 2026 | Aug 26, 2026 |
NYISO EL26-69 | filed change: yes | — | — | — | Nov 16, 2026 | Aug 26, 2026 |
MISO EL26-70 | filed change: yes | — | — | — | Nov 16, 2026 | Aug 26, 2026 |
CAISO EL26-71 | filed change: yes | — | — | — | Nov 16, 2026 | Aug 26, 2026 |
ISO-NE EL26-72 | filed change: yes | — | — | — | Nov 16, 2026 | Aug 26, 2026 |
ERCOT US-ERCOT-BATCH-ZERO | approved change: yes | 438,000 MW | — | — | Aug 31, 2026 | Aug 26, 2026 |
ONS BR-PNAST-2026-S1 | announced change: no | — | — | — | Sep 28, 2026 | Aug 26, 2026 |
AESO CA-AB-AESO-INTERIM | approved change: no | — | 1,200 MW | 1,200 MW | — | Aug 26, 2026 |
“—” means unresolved or not published; it does not mean zero.
7 of 9 records currently carry material_change=yes.
Governed large-load access is a continuing Frontier Grid practice. Compute is its clearest application because a project can have demand, capital, land, and announced generation while still failing at the access mechanism itself.
Project work follows the full path from grid and interconnection through fuel-backed power, physical deployment, utility obligations, financial gates, equipment, and capital sequencing.
The relevant question is whether every critical dependency can support the planned load, operating profile, target date, and downside case.
Queue timing, transmission, substations, deliverability, utility obligations, and the gap between announced power and executable service.
Generation configuration, implied fuel demand, physical gas delivery, transportation rights, contracts, competing demand, and stress economics.
Cooling, water, land, equipment, permitting, reliability, construction timing, and the local dependencies that can still govern first power.
Where utility commitments, construction, financing, customer demand, financial gates, and target operating dates fail to align.
The portal remains the compute research environment. It tracks market and node-level changes; project work applies the same evidence and dependency model to a specific large-load decision.
Selected nodes, signal summaries, constraint framing, and the public boundary of the compute research system.
Explore previewA source-backed sample of the Frontier Grid lens across interconnection, utility structure, and physical deliverability.
View PJM briefAnalysis of large-load tariff structure, financeability, contractual flexibility, and unresolved delivery risk.
View Missouri briefOngoing coverage of node-level signals, reversals, utility structures, and deployment-relevant constraints.
View Monthly DispatchBring the planned load, geography, target date, proposed power path, fuel assumptions, physical requirements, and the gates that remain unresolved.